Fort Saskatchewan KFS Deethanizer Addition Project

Facts and Figures:

  • Approximately 370 Tonnes
  • 11 QTY Modules + fully detailed grating, ladders and handrails
  • Project Duration – 4 months
  • Challenges - This project had extensive set-up to tailor to the Fabricator’s shop requirements, including FabTrol set-up and shop preferred details. Once in execution phase, the Approval and Shop issue schedule was very aggressive, making a minimum of one delivery per week on average
+
+
+
+